Collateral warranties for building design and construction
Contents |
[edit] What is a collateral warranty?
Collateral warranties are agreements that are associated with another 'primary' contract. They provide for a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract.
For a detailed legal definition of collateral warranties, see: Definition of collateral warranty.
[edit] Why are collateral warranties needed?
They came into being as a result of the courts deciding that defects in buildings were not recoverable in tort, as they were an economic loss which was only recoverable through a contractual relationship. Collateral warranties therefore create direct contractual relationships between parties that would not otherwise exist.
A typical example would be where an architect of a new office development owes a duty of care to an occupier of the development in so far as any subsequent defects which may arise are concerned. Privity of contract rules would prevent any liability arising between the architect and occupier without the existence of a collateral warranty.
[edit] What terms might a collateral warranty include?
There are a number of standard forms of collateral warranty (such as Joint Contracts Tribunal (JCT) collateral warranties), however there can be some dispute about their specific terms, with clients often claiming that industry standard warranties favour contractors and designers. There can also be difficulties with onerous terms that designers or contractors are unable to agree to as their insurers will not provide cover. As a consequence many collateral warranties are bespoke.
Collateral warranties may include 'step-in' rights allowing the beneficiary to step-into the role of the client. This can be important, for example to banks providing funding for a project, enabling them to ensure that the project is completed if the client becomes insolvent.
There may also be a contractual requirement for parties to obtain further warranties, for example there may be an obligation for the main contractor to obtain parallel collateral warranties from sub-contractors.
One of the disadvantages of collateral warranties is the difficulty in actually completing them. On large projects with many consultants and sub-contractors and multiple occupants, there can be a great number of warranties. The Contracts (Rights of Third Parties) Act can offer a way around this difficulty by allowing the primary contracts to confer benefits upon third parties even though they are not a party to that contract.
See also: Practical considerations of collateral warranties.
[edit] Case law relating to collateral warranties
[edit] Parkwood Leisure Limited v Laing
In the case of Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited in 2013, the judge found that Parkwood’s collateral warranty qualified as a 'construction contract' as the definitions were widely construed and so The Housing Grants, Construction and Regeneration Act applied to it as it covers all contracts related to the carrying out of construction operations.
The Housing Grants, Construction and Regeneration Act 1996 (HGRA - also known as the Construction Act) is intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly. The Act applies to all contracts for 'construction operations' (including consultants' appointments). If construction contracts fail to comply with the act, then the Scheme for Construction Contracts applies.
For more information see: Housing Grants, Construction and Regeneration Act
The court’s decision was an unexpected one for practitioners who assumed the Act did not apply to warranties.
For more information see: Parkwood Leisure Limited v Laing.
Collateral warranties will now be subject to greater scrutiny in the light of this case, with resistance from contractors and consultants to grant warranties and a desire to restrict the number and scope of warranties. That inevitably means further complications for the negotiation and drafting of warranties resulting in protracted and costly negotiations.
The upshot of this could now see the rise of third party rights as circumventing the issues surrounding collateral warranties.
For more information see: Rights of third parties.
See also: Difference between collateral warranties and third party rights.
[edit] Other cases
Other examples of case related to collateral warranties include:
- D&F Estates Limited and Others v Church Commissioners for England and others.
- Murphy v Brentwood District Council.
- Squibb Group Ltd v London Pleasure Gardens Ltd & Anor 2013.
- In 2024, the Supreme Court found that collateral warranties do not constitute construction contracts, overturning the 2022 ruling of the Appeal Court in the case of Abbey Healthcare v Simply Construction.
[edit] Related articles on Designing Buildings
- Agency.
- Appointing consultants.
- Collateral.
- Consultant switch.
- Construction contract.
- D&F Estates Limited and Others v Church Commissioners for England and others.
- Defects.
- Definition of collateral warranty.
- Design liability.
- Difference between collateral warranties and third party rights.
- Guarantees.
- Housing Grants, Construction and Regeneration Act.
- Murphy v Brentwood District Council.
- Novation.
- Parkwood Leisure Limited v Laing.
- Parent company guarantee.
- Performance bond.
- Practical considerations of collateral warranties.
- Scheme for Construction Contracts.
- Squibb Group Ltd v London Pleasure Gardens Ltd & Anor 2013.
- Step-in rights.
- Sub contractors.
- The Contracts (Rights of Third Parties) Act.
- Warranty.
[edit] External references
Featured articles and news
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Comments
To make a comment about this article, click 'Add a comment' above.
Separate your comments from any existing comments by inserting a horizontal line.
The supply chain is so long now it can be really difficult to get back to back warranties in place.